For the needs of foreign investor we provided:

  • Negotiating and adjustment of contract documents with construction supplier, expert assessment of tender offer
  • Organization of preparatory work connected with the beginning of the construction
  • Management of changes and additions to project documentation and construction activity
  • Administration, distribution and archiving of documents during the realization of the construction
  • Management of the construction process and the schedule of construction
  • Management and quality control
  • Management and cost control
  • Introduction of the system for final delivery of the building, technical support with taking the building over and final approval of construction.
  • Final account of the construction
  • Dubnica nad Váhom
  • 2015
  • 3 130 1m2
  • 221 m3
  • 115 tons

Gallery: Construction of hydropower plants VVE Ltd.

Construction of hydropower plants VVE Ltd. Construction of hydropower plants VVE Ltd. Construction of hydropower plants VVE Ltd. Construction of hydropower plants VVE Ltd. Construction of hydropower plants VVE Ltd. Construction of hydropower plants VVE Ltd. Construction of hydropower plants VVE Ltd. Construction of hydropower plants VVE Ltd. Construction of hydropower plants VVE Ltd.